Site Mitigation & Restoration Program

We protect and maintain California’s land and places
by setting strict standards for land restoration and cleanup

COVID-19 Updates 

Exide Residential Cleanup

DTSC is making progress in the neighborhoods near the former Exide battery recycling facility in Vernon.
We have prioritized homes, schools, parks and daycare centers for cleanup based on sampling results. To date we have completed the cleanup of all public schools and daycares with the highest levels of lead that granted us access. Most parks have been addressed, and we are cleaning up the soil at about 100 homes a month.

Three dozen crews are working in the neighborhoods of Bell, Boyle Heights, Commerce, East Los Angeles, Huntington Park, Maywood, and Vernon. These crews include more than 70 residents trained through the DTSC Workforce for Environmental Restoration in Communities program. DTSC staff are in the project area every day, keeping the residents involved and informed and overseeing contractors.

Cleanup involves removing lead-contaminated soil from the most-impacted properties and those where people’s risk of exposure is greatest. DTSC developed an interactive map that tracks the cleanup by parcel and provides soil sampling results.


For questions concerning the Residential Cleanup,
call the DTSC Exide Cleanup Project Information Hotline: (844) 225-3887
(If the Hotline number is not working, call (323) 803-2509)


For soil sampling data, go to our Soil Sampling Data for the Exide Preliminary Investigation Area web page.

Watch to learn more about the cleanup process and hear from residents

English

View the video from YouTube
(opens in a new window)

Español

Mire el video en YouTube
(Abrirá una nueva ventana)

Residential Cleanup and Investigation Progress
(as of June 19, 2020)

Residential Cleanup Progress

Total Parcels Cleaned

Of the 1,789 parcels cleaned:

  • 1,459 parcels cleaned up under the July 2017 Cleanup Plan
  • 330 parcels cleaned up under other Work Plans and Orders

Status of Parcels in the Cleanup Process

blue arrow

Number of parcels DTSC has permission to clean up:

  • Meeting conducted with owner/resident to discuss cleanup process and review options
  • Pre-excavation confirmation sampling scheduled
  • Agreements obtained to allow DTSC to conduct cleanup activities

Number of parcels ready for cleanup:

  • Pre-excavation confirmation samples collected
  • Property-specific plans prepared
  • Restoration materials selected by owner/resident
  • Relocation and interior cleanup options selected

Number of parcels scheduled for cleanup:

  • Pre-construction meeting conducted
  • Owner/resident finalizes restoration materials, relocation and interior cleanup options
  • Cleanup scheduled two to four weeks in advance

Number of crews:

  • Crews active in the field working on soil cleanup activities and/or restoration and landscaping of the property

Investigation Progress

Parcels Sampled (8,555)
84%
Parcels that DTSC has Permission to Sample (9,005)
89%
Parcels Within the Preliminary Investigation Area (PIA) (10,158)
100%

 

Cleanup Plan & Final Environmental Impact Report

COVID-19 Advisory

COVID-19 Advisory, DTSC Field Activities 

Project Labor Agreement

Project Labor Agreement By and Between DTSC, the Los Angeles/Orange Counties Building and Construction Trades Council, and the Signatory Craft Councils and Unions for the Exide Cleanup Project (June 2018).

How to Sign Up for Soil Testing

Step 1

Check to see if you live within the 1.7 mile radius shown on this map. You can also call DTSC at 1-844-225-3887 to find out. Only properties within this 1.7 mile area are eligible for soil testing at this time.

Step 2

If you live within the 1.7 mile area, owners or tenants can give permission for soil testing by signing an Access Agreement. Select the appropriate form below:

Step 3

Once you have filled out the Access Agreement, print it, sign it, and send a paper copy to DTSC at the following address:

Attention: DTSC – Exide Cleanup Team
Department of Toxic Substances Control
8800 Cal Center Drive
Sacramento, CA 95826

If you have any questions, call 844-225-3887.

Step 4

  • Once the access agreement is received, DTSC will contact you to schedule soil testing.
  • The testing crew will take five small samples of soil in your front and back yard and will also test your outside paint for lead. You do not need to be home for the testing.
  • Once the soil test results are confirmed, DTSC will let you know if your yard will require cleanup.
  • If cleanup is needed, DTSC will schedule a convenient date for you. It takes about a week to remove the contaminated soil, replace it with clean soil, and re-landscape. After the cleanup, DTSC offers an interior cleaning with a HEPA vacuum, and other surfaces cleaned to remove dust.
  • Steps in Exide Sampling and Cleanup
 

Videos

Lead Contamination Cleanup: Preliminary Area of Investigation

Limpieza Residencial Exide

DTSC está progresando en los vecindarios cercanos a la antigua instalación de reciclaje de baterías Exide en Vernon. Hemos priorizado hogares, escuelas, parques y guarderías infantiles para la limpieza basada en resultados de muestreo. Hasta la fecha, hemos completado la limpieza de todas las escuelas públicas y guarderías con los niveles más altos de plomo que nos han proporcionaron acceso. La mayoría de los parques se han investigado, y estamos limpiado el suelo en aproximadamente 100 hogares al mes.

Tres docenas de cuadrillas trabajan en los vecindarios de Bell, Boyle Heights, Commerce, East Los Angeles, Huntington Park, Maywood y Vernon. Estas cuadrillas incluyen más de 70 residentes locales capacitados a través del programa DTSC Workforce for Environmental Restoration in Communities. El personal de DTSC está presente diario en el área del proyecto informando e involucrando a los residentes y supervisando a los contratistas.

La limpieza implica eliminar el suelo contaminado con plomo de las propiedades más afectadas y aquellas con el mayor riesgo de exposición a personas. DTSC desarrolló un mapa interactivo que rastrea la limpieza por parcela y proporciona resultados de muestreo de suelo.

Progreso de la Investigación y Limpieza Residencial
(hasta el 19 de juno del 2020)

Progreso de la Limpieza Residencial

Total de parcelas completadas

De las 1,789 parcelas limpiadas:

  • 1,459 parcelas completadas bajo el plan de limpiza aprobado en julio del 2017
  • 330 parcelas completadas bajo otros planes u ordenes de trabajo

Estatus de las Parcelas en el Proceso de Limpieza Datos

blue arrow

Numero de parcelas donde DTSC ha adquirido el acceso para llevar acabo la limpieza:

  • Reunión realizada con el propietario/residente para revisar el proceso de limpieza y las opciones disponibles
  • Se ha agendado una fecha para tomar muestras de confirmación
  • Acuerdos obtenidos para permitir que DTSC lleve a cabo las actividades de limpieza

Numero de parcelas listas para las actividades de limpieza:

  • Se ha tomado las muestras de confirmación previas a la excavación
  • Planes especificos de la propiedad preparados
  • Materiales de restauración seleccionados por el propietario/residente
  • Se seleccionaron las opciones de reubicación y limpieza interior

Numero de parcelas programadas para la limpieza:

  • Reunión previa a la construcción realizada
  • Propietario/residente ha confirmado los materiales de restauración, la reubicación y las opciones de limpieza interior
  • Limpieza programada dos a cuatro semanas por adelantado

Numero de cuadrillas:

  • Cuadrillas activas en el campo trabajando en actividades de limpieza de suelos y / o restauración y paisajismo de la propiedad

Progreso de la Investigación

Parcelas muestreadas (8,555)
84%
Parcelas que DTSC tiene permiso de muestrear (9,005)
89%
Parcelas dentro del Área de Investigación Preliminar (PIA) (10,158)
100%

 

Plan de Limpieza Residencial de Exide Final y el Reporte de Impacto Ambiental

Como Inscribirse Para El Muestreo De Suelo

Primer Paso

Verifique si vive dentro del 1.7 milla en este mapa. También puede llamar a DTSC al 1-844-225-3887 para más detalles. Solamente propiedades dentro del 1.7 milla están elegibles para el muestreo de suelo a este momento.

Segundo Paso

Si viven dentro de la 1.7 milla, propietarios o inquilinos pueden dar permiso para el muestreo de suelo firmando el Acuerdo de Acceso. Seleccione el formulario apropiado debajo:

Tercer Paso

Después de llenar el Acuerdo de Acceso, imprímelo, fírmelo y mande una copia al domicilio de DTSC:

Atención: DTSC –Exide Cleanup Team
Departamento de Control de Sustancias Tóxicas
8800 Cal Center Drive
Sacramento, CA 95826

Si tienes preguntas, llame al 844-225-3887.

Que Esperar Despés

  • Después de recibir el formulario de acuerdo de acceso, DTSC se comunicara con usted para hacer una cita del muestreo de suelo.
  • Los trabajadores tomaran cinco pequeñas pruebas de suelo enfrente y en el patio interior y también tomaran pruebas de plomo de la pintura exterior. No necesita de estar en su casa para las pruebas.
  • Después de que las pruebas de suelo sean confirmadas, DTSC le dejara saber si su propiedad necesita limpieza.
  • Si la propiedad necesita limpieza, DTSC hará una cita conveniente para usted. Se demora como una semana para remover el suelo contaminado y reemplazarlo con suelo limpio y reformar el jardín. Después de la limpieza, DTSC le ofrece una limpieza interior con una aspiradora HEPA y otras superficies limpiadas para eliminar el polvo.
  • Pasos para la toma de muestras y limpieza de Exide

Video

Limpieza de Contaminación de Plomo: Investigación de la Área Preliminar